A Cross Connection Control Program assists in maintaining good quality drinking water. Backflow Prevention devices are an important component of the City of Oneida Water Department’s Cross Connection Control Program. Following are links to the Backflow Prevention Device Application Documents that should be submitted to the City of Oneida Water Department. If you are uncertain as to whether you should complete and submit these documents, please contact the City of Oneida Water Department at 315-363-1490.

The City of Oneida Water Department will NOT begin construction of your water service until Department of Health approval of the backflow plan is received. Please allow 4 to 6 weeks for the review process.

The City of Oneida Water Department’s Backflow Prevention (BFP) device design approval is a THREE-STEP process:

First Step – Initial Review: Submit your application documents to the City of Oneida Water Department in PDF format via email to acampany@oneidacityny.gov. Please complete and include the City of Oneida Water Department’s checklist to ensure that you have fulfilled all of the requirements. For the initial review you do not need to have the owner or design professional sign or stamp the submittals. The Water Superintendent will review them and be in contact with any questions, issues, or changes needed.

When preparing the submittal, your design professional should follow the guidance outlined in the NYSDOH guidelines on Cross Connection Control, including all of the drawing specifications (link below).

Email the BFP Design Application submittal documents to acampany@oneidacityny.gov.  Please include the property address in the subject line

A) City of Oneida Water Department’s Checklist

B) Application (DOH Form 347 – Application for Approval of Backflow Prevention Devices)

C) Site Plan and Location Plan

D) Plumbing Floor Plan

E) BFP Elevation Plan and Plan View Details

F) City of Oneida Water Department’s Engineering Report Form – Include any additional narrative to broaden the understanding of the proposed project or to clarify points noted in the form

G) City of Oneida Commercial Property Service and Meter Sizing Sheet (if applicable)

H) Manufacturer’s data sheets for BFP device(s) with FCCCHR of USC noted on the sheets

I) Manufacturer’s data sheets for “hot box”, if applicable.

Second Step – Final Review: Once the submittals are found approvable by the City of Oneida Water Department, we will ask you to send us four (4) hard copies of all submittals (with any final revisions necessary). The final submittals need to have all the required signatures, dates, and P.E./R.A. stamps. Once we receive the final hard copies, we will complete our final review, sign our portion of the DOH 347 form, and forward all four (4) copies of the submittals to the County Health Department for their review and final approval. They will in turn contact you with any issues and/or send you back a DOH stamped approved copy for your records.

Third Step – Certification of Installation: Please note the required initial and annual testing report form (DOH 1013) must be fully completed after installation of the device. After initial installation of the device, the owner’s design professional must complete the DOH 1013 form (Parts A & B) certifying that the device was installed per the approved BFP plans. Submit this initial test report to the City of Oneida Water Department (within 45 days of installation) and to the appropriate County Department of Health.

Additionally, the BFP device(s) is required to be tested annually by a NYSDOH-certified tester, and copies of the test report(s) shall be submitted to the City of Oneida Water Department and the County Department of Health (only Part A needs to be completed annually).

To use the forms 1 through 3 below – download or save the attachments to a locatable folder on your device. Then complete and send them to the City of Oneida Water Department via email to water@oneidacityny.gov . Utilize the links to assist with information required for the completed submittal.
Doc app

Document Center

The Document Center provides easy access to public documents. Click on one of the categories below to see related documents or use the search function.

Categories always sorted by seq (sub-categories sorted within each category)
Documents sorted by SEQ in Ascending Order within category

Backflow Prevention Device Application Documents5 documents

  • Checklist for Backflow Preventor Approval
    document seq 0.00
  • DOH347-Application for Approval of Backflow Prevention Devices
    document seq 0.00
  • Engineers Report Form
    document seq 0.00
  • Property Service and Meter Sizing Sheet
    document seq 0.00
  • DOH1013– Parts A and B to be completed after installation
    document seq 0.00